Sunrise Coal - Carlisle Mine / Slurry Impoundment Reconstruction
/Sunrise Coal Company wanted to modify and reconstruct portions of their coal fine slurry impoundment cell. The project involved lowering the crest height by 10 feet, reducing the top width by 20 feet, and laying the interior slope to 2.7:1 side slope. The material excavated from the existing levee was then utilized to construct an earthen buttress along the tow of the exterior levee slope. Other activities on this project included the installation of a new primary spillway riser pipe, a grouted rip rap stilling basin, underdrains, ditch relocations, and mulched seeding.
Excavated 430,000 CY of compact fill material
Installed 28,000 tons of gravel
Removed and Replaced 90,000 CY of topsoil
Installed 23,000 LF of drainage
Permanently mulched 40 acres
Installed new 36-inch diameter pond riser